Activity 3.2

Construction and installation of the prototype composting system to the Municipality of Tinos

Activity 3.2 foresees the construction and installation of the prototype composting unit, developed and designed during Activity 2.2.

The pilot composting system is an in-vessel reactor system, designed by NTUA. The construction of the demonstration unit took place in Athens under the responsibility of NTUA. After the completion of the system construction, the entire prototype composting unit was transferred and installed at Tinos Island, on July 28th 2014.

A notice board (2nd notice board) has been designed to be displayed near the setting place of the demonstration unit, bearing the LIFE logo and the logo of the project.

Prototype composting unit, installed at the area of the project implementation, in Tinos island LIFE+ signboard for prototype composting unit